Florida is considering construction of a flood control dike


Florida is considering construction of a flood control dike having a life span of 16 years. The investment require is $60,00 and annual maintenance costs of $5,000. The project will provide no benefits for the first two years but will save $24,000 per year in flood damage starting in the third year. The appropriate MARR is 12%. 1) What is the annual value of the investment cost? Term 1 $6,897 $8,604 $5,678 $7,675 1.53 1.76 2.20 1.33 2) What is the B/C ratio for this project? Term 2 $6,897 $8,604 $5,678 $7,675 1.53 1.76 2.20 1.33