Flames Corp. contracted to build a bridge for $5,000,000. Construction began in 2017 and was completed in 2018. Data relating to the construction are:

2017 2018

Costs incurred $1,620,000 $1,400,000

Estimated costs to complete 1,380,000 -

Required: Using the percentage-of-completion method and the cost-to-cost basis, refer to BE6-30, E6-30, study guide E6-6 as a guide.

a) How much revenue should be reported for 2017? Show your calculation.

b) Prepare the journal entry to record progress billings of $1,700,000 during 2017.

c) Prepare the journal entry to record the revenue and gross profit for 2017.

d) How much gross profit should be reported for 2018? Show your calculation.