Finds working on a project to clear 25 hectares of


Fajar S.A., is an industrial waste cleaning company. They are currently working on a project to clear 25 hectares of vegetation. At this precise moment, they have cleared 18 hectares. The contract requires to complete the work on fifty weeks, on a budget of $ 50,000. Each week they work 40 hours and the estimated cost in these tasks is $ 25 / hour. Fajar understands that the time to clean one hectare follows the model of the learning curve, but only has information about the required times of hectares 17 and 18 (assume that they worked in that same order): they required 48 and 45 hours, respectively. Explain whether Fajar can meet the project requirements (duration and total cost).