Finding of the labor rate variance


Borden Enterprises uses standard costing. For the month of April, the company reported the following data:

• Standard direct labor rate: $10 per hour
• Standard hours allowed for actual production: 8,000 hours
• Actual direct labor rate: $9.50 per hour
• Labor efficiency variance: $4,800 Favorable

The labor rate variance for April is:

A. $3,760 U

B. $3,760 F

C. $2,850 F

D. $2,850 U

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Finding of the labor rate variance
Reference No:- TGS052250

Expected delivery within 24 Hours