Leach Distributors packages and distributes industrial supplies. A standard shipment can be packaged in a class A container, a class K container, or a class T container. A single class A container yields a profit of $9; a class K container, a profit of $7; and a class T container, a profit of $15. Each shipment prepared requires a certain amount of packing material and a certain amount of time.

Resources needed per segment shipment
Class of Container       Packing Material (Pounds)      Packing Time (Hours)

A                                                     2                                         2
K                                                     1                                         6
T                                                     3                                         4

Hugh Leach, head of the firm, must decide the optimal number of each class of container to pack each week. He is bound by the previously mentioned resource restrictions but also decides that he must keep his 6 full-time packers employed all 240 hours (6 workers 3 40 hours) each week. Formulate and solve this problem using LP software.

 Provide complete and step by step solution for the question and show calculations and use formulas.

Solution Preview :

Prepared by a verified Expert
Operation Research: Finding amount of packing material in certain amount of time
Reference No:- TGS01953874

Now Priced at $30 (50% Discount)

Recommended (92%)

Rated (4.4/5)