Find which activities are on the critical path


A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A3 - B11 - C7 A D 13 B, C E10 B F6 D G5 E H 8 F, G

a. Draw the network diagram.

b. Calculate the slack for each activity. Which activities are on the critical path?