Find total machine time needed if operations times are given


Problem:

The normal scrap loss for four successive operations is 5%, 3%, 15%, and 10% respectively.

Question 1) How many units should be started through in order to finish with 1,200 pieces?

Question 2) Find:

i) The total machine time needed if the operations times are 3,6, 4, and 5 minutes respectively.

ii) The total cost if the cost per unit for each successive operation is $2, $5, $3, and $1, respectively

Solve the problem and show all work.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Find total machine time needed if operations times are given
Reference No:- TGS0881032

Expected delivery within 24 Hours