Find the standard time for the operation


Problem: An analyst has timed a metal cutting operation for 50 cycles. The average time per cycle was 10.40 minutes, and the standard deviation was 1.20 minutes for a worker with a performance rating of 125 percent. Assume an allowance of 16 percent of job time. Find the standard time for this operation.

Solution Preview :

Prepared by a verified Expert
Microeconomics: Find the standard time for the operation
Reference No:- TGS01744523

Now Priced at $20 (50% Discount)