Find the standard time for operation


Discuss the below:

Q: An analyst has timed a metal-cutting operation for 50 cycles. The average time per cycle was 10.7 minutes, and the standard deviation was 1.20 minutes for a worker with a performance rating of 133 percent. Assume an allowance of 15 percent of job time. Find the standard time for this operation.