Find the slack time individual activity and critical path


Shirley Hopkins is developing a program in leadership training for middle managers. Shirley has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table.

Activity Immediate Predecessor Time (Days)
A - 2
B - 5
C - 1
D B 10
E A,D 3
F C 6
G E,F 8

a. Develop an AON network for this problem.
b. What is the critical path?
c. What is the total project completion time?
d. What is the slack time for each individual activity?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Find the slack time individual activity and critical path
Reference No:- TGS092706

Expected delivery within 24 Hours