Find the schedule and cost variances for a project


Find the schedule and cost variances for a project that has an actual cost at month 22 of $540,000, a schedule cost of $523,000 and an earned value of $535,000.

A software development project at day 70 exihibits an actual cost of $78,000 and a scheduled cost of $84,000. The foreman estimates a value completed of $81,000. What are the cost and schedule variances and the CSI. Estimate the time variances.