Find the projects modified internal rate of return


Question 1: Consider a project with the following expected cash flows:

Year    Cash flow
0    - $400,000
1      $100,000
2      $120,000
3      $850,000

If the discount rate is 0%, what is the project's net present value?
If the discount rate is 2%, what is the project's net present value?
If the discount rate is 6%, what is the project's net present value?
If the discount rate is 11%, what is the project's net present value?

What is this project's modified internal rate of return?

Question 2: Consider a project with the expected cash flows:

Year    Cash flow
0    -$815,000
1     $141,000
2     $320,000
3     $440,000

What is this project's internal rate of return?
If the discount rate is 1%, what is this project's net present value?
If the discount rate is 4%, what is this project's net present value?
If the discount rate is 10%, what is this project's net present value?
If the discount rate is 18%, what is this project's net present value?

Question 3: A project requiring a $4.2 million investment has a profitability index of 0.94. What is its net present value?

Solution Preview :

Prepared by a verified Expert
Finance Basics: Find the projects modified internal rate of return
Reference No:- TGS02048374

Now Priced at $25 (50% Discount)

Recommended (92%)

Rated (4.4/5)