Find the minimum number of kanbans needed


Discuss the below in detail:

Q: Material handlers use forklifts to move parts on pallets around a plant. A pallet is used as the minimum produc­tion quantity - each pallet holds 40 parts. Replenishment lead time for a part is 2 hours and its demand rate is 1200 units per 8 hour day.

a) Find the minimum number of kanbans needed for this part.

b) Suppose that a 10% safety factor is desired. How many kanbans are needed?