Find the earliest and latest event times for the events in


Bibb and Tukka own and operate a successful chain of clothing stores. They plan to open a new outlet. The activities involved are listed below with the activities that must precede them and their durations.

866_37c2aa1d-44c4-42a4-9647-d08d77bad389.png

(a) Compile a network diagram to represent this venture.

(b) Find the earliest and latest event times for the events in your network, and use them to identify the minimum duration of the project and the activities that are on its critical path.