Find the critical path and the estimated completion time


Assignment:

Q: Here are the precedence requirements, normal and crash times and costs for a construction project.

Activity

Preccdim g Activity

Time (weeks) Nonnal   Crash

Cost (S)
Normal      Crash

A

-

4

2

10.000

11,000

B

A

3

2

6.000

9.000

C

A

4

1

4,000

6,000

D

B

5

3

14.000

18,000

E

D,C

2

1

9,000

10.000

Draw the AON network, find the critical path and the estimated completion time.

How much slack time does Activity C have without delaying the project completion time?

To shorten the project by one week, which activity would be shortened and what would the final total

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Find the critical path and the estimated completion time
Reference No:- TGS02053191

Expected delivery within 24 Hours