Find scheduled completion time and the critical path


The following data were obtained from a project to build a pressure vessel:

Activity Duration Predecessors
A 4 weeks ---
B 4 weeks ---
C 3 weeks B
D 2 weeks A, C
E 3 weeks B
F 5 weeks D, E, G
G 2 weeks B
H 6 weeks F
I 3 weeks G
J 1 week I

Construct a network for the project.
(A.) Calculate the scheduled completion time and identify the critical path.
(B.) What is the slack time (float) for activities A, D, E, and G?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Find scheduled completion time and the critical path
Reference No:- TGS090807

Expected delivery within 24 Hours