Find probability project manager able to complete project


Problem:

Consider a project where Expected time is 43 days and standard deviation of the project is 8 days. The project manager has agreed to deliver the project by 41 days. What is the probability the project manager would be able to complete the project in 41 days? Solve the problem and show all work.