Find out the multi-factor productivity for tires


Discuss the below:

Q: Rubber Meets the Road produces motorcycle tires. They make 1200 tires per day with the following resources: 400 labor hours per day paying $12 per hour; 20,000 pounds per day of raw material at a cost of $1.50 per pound; $5,000 per day for electricity; and $10,250 per day for capital expense. What is the multi-factor productivity for these tires?

The change in Productivity for the above problem if they are able to reduce the energy bill by $950 per day without cutting production?