Find mass flow rate of water vapor-final relative humidity


Moist air initially at 70 percent humidity and 5 C is heated to 25C. The input flow rate is 3000 cubic meters per hour, and the pressure is 100 kPa. Using the air table and the steam tables, find

(a) the mass flow rate of water vapor in kg/s,

(b) the heat transfer needed in kW,

(c) the final relative humidity.