Find cumulative lead time for r is how many days


Each R requires 2 components S and 1 part T. The lead time for assembly at R is 3 days. The lead time for the manufacture of S is 5 days. The lead time for the manufacture of T is 10 days.
The cumulative lead time for R is how many days?

A.6
B.9
C.13
D.17
E.Cannot be determined