Find critical path and estimate project-s completion time


The following information is available about a project:

Activity Activity Time
(Weeks) Immediate
Predecessor(s)
A 3 ----
B 4 ----
C 6 A
D 9 B
E 6 B
F 10 C,D
G 8 D,E
H 9 G,F

a) Draw the network diagram.

b) Find the critical path and estimate the project's completion time. Why is it important for a project manager to identify the critical path?

c) Calculate the slack for each activity. Why is it important for a project manager to know the slack of activities?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Find critical path and estimate project-s completion time
Reference No:- TGS082818

Expected delivery within 24 Hours