Fastball delivery company acquired an adjacent lot to


Fastball Delivery Company acquired an adjacent lot to construct a new warehouse, paying $30,000 and giving a short-term note for $270,000. Legal fees paid were $1,425, delinquent taxes assumed were $12,000, and fees paid to remove an old building from the land were $18,500. Materials salvaged from the demolition of the building were sold for $4,500. A contractor was paid $910,000 to construct a new warehouse. Determine the cost of the land to be reported on the balance sheet.