Explanation of why the static budget was not achieved


Problem:

The budgeted prices for materials and direct labor per unit of finished product are $11 and $55, respectively. The production manager is delighted about the following data:

The budgeted prices for materials and direct labor per unit of finished product are $11 and $55, respectively. The production manager is delighted about the following data:

                         Static Budget      Actual Costs        Variance
Direct materials       77,000             72,000                5,000
Direct Labor            35,000              32,000               2,400

Is the manager's happiness justified? Prepare a report that might provide a more detailed explanation of why the static budget was not achieved. Good output was $5,800 units.

Solution Preview :

Prepared by a verified Expert
Finance Basics: Explanation of why the static budget was not achieved
Reference No:- TGS02040812

Now Priced at $25 (50% Discount)

Recommended (90%)

Rated (4.3/5)