Explain the estimated activity-base information


Adirondack Corporation is estimating activity costs associated with producing two different sized e-reader tablets. The indirect labor can be traced to three separate activity pools. The budgeted activity cost and activity base information, along with the estimated activity-base information, is provided below.  All work must be shown for credit.

 

Activity

Cost

 

Activity Base

 

Purchasing

$  300,000

Number of purchase orders

 

Materials handling

  500,000

Number of moves

 

Production

1,500,000

Machine hours

 

TOTAL                                        $2,300,000

 

 

Number of

Purchase

Orders

 

Number

of

Moves

 

 

Machine

Hours

 

Number

of

Units

 

7" tablet

4,000

1,400

2,000

2,000

 

10' tablet

4,000

  800

8,000

4,000

 

TOTALS

8,000

2,200

10,000

6,000

 