explain procedure to take shut down and to test


Explain procedure to take shut down and to test the power line before starting work?

Ans: Study the circuit and find out the circuit breaker to be opened. Open and lock the circuit breaker and take the key in personnel custody. Disconnect neutral link if available. Hang "Man at Work" notice board on the circuit breaker. Test for supply after making sure that, the testing device itself is OK at the line or equipment . Start the work.

Request for Solution File

Ask an Expert for Answer!!
Electrical Engineering: explain procedure to take shut down and to test
Reference No:- TGS0286820