Explain and illustrate the changes needed


Solve the below:

Q: A make-to-stock product (call it product A) is made of two components; one unit of B and two units of C.

Bismade of two units of D,on eunit E,and four units of F.

Cismade of one unit of D and two units of E. Items C and F have lead times of one week, and items A, B, E, and D have two-week lead times. Lot-for-lot 1 sizing is used for items A, D, and E; lots of size 50, 100, and 50 are used for items B, C, and F, respectively. Items A, C, D, and E have on-hand (beginning) inventories of 10, 3, 50, and 20, respectively; all other items have zero beginning inventory. The company is scheduled to receive 20 units of A in Week 1, 30 units of C in Week 1, and 400 units of D in Week 3; there are no other scheduled receipts. Thirty spare units of component E are required in week 4.

Explain and illustrate (using MRP records) if an order of 60 units of A could be fulfilled in week 9.

Once in week 1, the company's planner received a message stating that all Schedules Receipts will be delayed by one week. Also, he/she received the information that the demand for week 10 will be 40 units. Explain and illustrate the changes needed.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Explain and illustrate the changes needed
Reference No:- TGS02040024