Evan schwartz has 6 jobs waiting to be processed through


Evan Schwartz has 6 jobs waiting to be processed through his machine. Processing time (in days) and due date information for each job are as follows:

a 2 3

b 1 2

c 4 12

d 3 4

e 4 8

f 5 10

Sequence the jobs by FCFS, SPT, SLACK, and DDATE. Calculate the mean flow time and mean tardiness of the six hobs under each sequencing rule. Which rule would you recommend?