Evaluate the various configurations of operating and closed


Problem - Andrew-Carter, Inc

Andrew-Carter, Inc. (A-C), is a major Canadian producer and distributor of outdoor lighting fixtures. Its products are distributed throughout South and North America and have been in high demand for several years. The company operates three plants to manufacture fixtures and distribute them to five distribution centers (warehouses). During the present global slowdown, A-C has seen a major drop in demand for its products, largely because the housing market has declined. Based on the forecast of interest rates, the head of operations feels that demand for housing and thus for A-C's products will remain depressed for the foreseeable future. A-C is considering closing one of its plants, as it is now operating with a forecast excess capacity of 34,000 units per week. The forecast weekly demands for the coming year are as follows:

Warehouse 1

9,000 units

Warehouse 2

13,000

Warehouse 3

11,000

Warehouse 4

15,000

Warehouse 5

8,000

Plant capacities, in units per week, are as follows:

Plant 1, regular time

27,000 units

Plant 1, on overtime

7,000

Plant 2, regular time

20,000

Plant 2, on overtime

5,000

Plant 3, regular time

25,000

Plant 3, on overtime

6,000

If A-C shuts down any plants, its weekly costs will change, because fixed costs will be lower for a non-operating plant. Table   13.9 shows production costs at each plant, both variable at regular time and overtime, and fixed when operating and shut down. Table 13.10 shows distribution costs from each plant to each distribution center.

Discussion Questions

1. Evaluate the various configurations of operating and closed plants that will meet weekly demand. Determine which configuration minimizes total costs.

2. Discuss the implications of closing a plant.

Table 13.9 Andrew-Carter, Inc. Variable costs and Fixed Production costs per week

Plant

Variable Cost (per unit)

Fixed cost per week

Operating

Not Operating

1, regular time

$2.80

$14,000

$6,000

1, overtime

3.52

-

-

2, regular time

2.78

12,000

5,000

2, overtime

3.48

-

-

3, regular time

2.72

15,000

7,500

3, overtime

3.42

-

-

 

Table 13.10 Andrew-Carter, Inc. Distribution Costs per unit

From Plants

To Distribution Centers

W1

W2

W3

W4

W5

1

$.50

$.44

$.49

$.46

$.56

2

.40

.52

.50

.56

.57

3

.56

.53

.51

.54

.35

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Evaluate the various configurations of operating and closed
Reference No:- TGS02159158