Estimated cost function


Problem: Ken Howard, financial analyst at JVR Corporation, is examining the behavior of quarterly maintenance costs for budgeting purposes. Howard collects the following data on machine-hours worked and maintenance costs for the past 12 quarters:

Quarter    Machine-Hours    Maintenance Costs
1 - 90,000    $185,000
2 - 110,000    $220,000
3 - 100,000    $200,000
4 - 120,000    $240,000
5 - 85,000    $170,000
6 - 105,000    $215,000
7 - 95,000    $195,000
8 - 115,000    $235,000
9 - 95,000    $190,000
10 - 115,000    $225,000
11 - 105,000    $180,000
12 - 125,000    $250,000

Q1. Estimate the cost function for the quarterly data using the high-low method.

Q2. Plot and comment on the estimated cost function.

Q3. Howard anticipates that JVR will operate machines for 90,000 hours in quarter 13. Calculate the predicted maintenance costs in quarter 13 using the cost function estimated in #1.