Estimate the variances and what do they say about the


A project to build a new taxiway at Culpepper Airport is 5 days behind at day 65. It had a planned cost of $735,000 for this point in time, but the actual cost is only $550,000. Estimate the variances and what do they say about the health of the project? Re-estimate if the actual cost to date had been $750,000.