Slonaker Inc. has provided the following data concerning its maintenance costs:
  | 
Machine-Hours | 
Maintenance Cost | 
| April | 
5,800 | 
$30,380 | 
| May | 
5,783 | 
$30,290 | 
| June | 
5,765 | 
$30,238 | 
| July | 
5,762 | 
$30,234 | 
| August | 
5,718 | 
$30,079 | 
| September | 
5,796 | 
$30,361 | 
| October | 
5,811 | 
$30,390 | 
| November | 
5,802 | 
$30,379 | 
| December | 
5,786 | 
$30,319 | 
 
 | 
Management believes that maintenance cost is a mixed cost that depends on machine-hours.
Required:
Estimate the variable cost per machine-hour and the fixed cost per month using the high-low method.(Round your "Variable cost" to 2 decimal places. Omit the "tiny_mce_markerquot; sign in your response.)
Variable cost per machine-hour	$
Fixed cost per month	$