Estimate the process standard deviation


Bath concentrations are measured hourly in chemical process. Data(in ppm) for last 32 hours are shown in below data (please read down the columns to understand the order that the measurements were taken.) The process target is ?0=175

160 186 190 206

158 195 189 210

150 179 185 216

151 184 182 212

153 175 181 211

154 192 180 202

158 186 183 205

162 197 186 197

a) Estimate the process standard deviation.

b) Set up and apply an EWMA control chart to the data usig lambda = 01 and L = 27

c) Plot the EWMA chart and interpret the chart

Request for Solution File

Ask an Expert for Answer!!
Basic Statistics: Estimate the process standard deviation
Reference No:- TGS0868198