Estimate the learning rate


Problem: You have just completed a pilot run of 10 units of a major product and found the processing time for each unit was as follows:

UNIT   NUMBER TIME (HOURS )

1                   970
2                   640
3                   420
4                   380
5                   320
6                   250
7                   220
8                   207
9                   190
10                 190

1) According to the pilot run, what would you estimate the learning rate to be?

2) Based on a , how much time would it take for the next 190 units, assuming no loss of learning?

3) How much time would it take to make the 1,000th unit?

Solution Preview :