Estimate the learning curve based on pilot run


As an operation manager for new generation Laser Inc., you have just completed a pilot run of 10 new lasers, where each unit processing time was as follows.

Unit Number Time (hours)
1 985
2 640
3 420
4 415
5 320
6 290
7 245
8 270
9 190
10 160

Based on the pilot run, estimate the learning curve.