Estimate the amount of time needed to complete - the work


Learning curve Online Homework Question

1. An aircraft company has an order to refurbish the interiors of 16 jet aircraft. The work has a learning curve percentage of 90. On the basis of experience with similar jobs the industrial engineering department estimates that the first plane will require 250 hours to refurbish. Estimate the amount of time needed to complete:

The fourth plane.

a. 190 to 193

b. 200 to 203

c. 250 to 253

2. The first four planes.

a. 876 to 879

b. 880 to 885

c. 886 to 890

3. The work has a learning curve percentage of 92.The fourth plane.

a. 205 to 210

b. 210 to 215

c. 215 to 220

Solution Preview :

Prepared by a verified Expert
Financial Accounting: Estimate the amount of time needed to complete - the work
Reference No:- TGS02596100

Now Priced at $10 (50% Discount)

Recommended (98%)

Rated (4.3/5)