Equivalent units for the materials unit cost calculation


Problem:

Stanley Company adds materials at the beginning of the process in Department M. Data concerning the materials used in the March production follows:


Units

Work in process at March 1

15,000

Started during March

38,000

Completed and transferred to next department during March

37,000

Normal spoilage incurred

2,000

Work in process at March 31

14,000

Required

Question: Using the average cost method, the equivalent units for the materials unit cost calculation are:

  • 38,000.
  • 51,000.
  • 55,000.
  • 37,000.

Note: Be sure to show how you arrived at your answer.