Earned value fundamentals


Assignment:

Earned Value Fundamentals

Describe the linkages of the work breakdown structure and the time-phased budget to arrive at an earned value analysis. What is the impact on earned value if the cost estimation is significantly lower because of low estimates or specification changes in the project? Provide examples of projects you have been involved with or read about that may have had this problem.

Earned Value Problems

Of the three problems below, choose and solve one problem. Show your work. Along with your answer, define each term and explain the significance (meaning) of the solution.

Question 1. During a project, Earned Value Analysis is performed and gives the following numbers:

EV: 523,000; PV: 623,000; AC: 643,000.

Which results are correct?

A. CV: +120,000; SV: +100,000

B. CV: +100,000; SV: +120,000

C. CV: -100,000; SV: -120,000

D. CV: -120,000; SV: -100,000

Question 2. You found the following Earned Value Analysis information for a recently closed out project:

SPI = 0.7, CPI = 1.0

A. The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.

B. The project's deliverables have all been finished. The project came in ahead of schedule but on budget.

C. The project's deliverables have all been finished. The project came in on schedule but over budget.

Question 3. You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile been finished.

You perform Earned Value Analysis and find the following results:

EV: 250,000; PV: 200,000; AC 275,000

BAC is 500,000.

What is right?

A. EAC = 550,000

B. EAC = 525,000

C. EAC = 500,000

D. EAC = 425,000

Solution Preview :

Prepared by a verified Expert
Business Management: Earned value fundamentals
Reference No:- TGS01827189

Now Priced at $30 (50% Discount)

Recommended (97%)

Rated (4.9/5)