Eakins enterprises makes model boats and it is switching to


Eakins Enterprises makes model boats, and it is switching to a lean manufacturing process. At one assembly area, Eakins is using one part container that holds 250 parts and it wants the output to be approximately 100 finished parts per hour; they also desire 10 percent safety stock for this part. How fast will the container have to make it through the system to accomplish this?