Each of the methods in part a determine 1 the average


Job Job Time (Days) Due Date (Days)
A 14 19
B 10 16
C 7 15
D 5 17

Each of the methods in part a, determine (1) the average job flow time, (2) the average tardiness, and (3) the average number of jobs at the work center.

Round your intermediate calculations also final answers to 2 decimal places.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Each of the methods in part a determine 1 the average
Reference No:- TGS0974148

Expected delivery within 24 Hours