During the weekly reporting one person gives the status of


Progress reports are critical in monitoring progress. During the weekly reporting, one person gives the status of an 8-day task as 50% complete and 5 days remaining on the work. How many ways could this be interpreted and what are the implications of reading it the wrong way?