During 2012 sand inc expected job no 51 to cost 300000 of


Question - During 2012, Sand, Inc. expected Job No. 51 to cost $300,000 of overhead, $500,000 of materials, and $200,000 in labor. Sand applied overhead based on direct labor cost. Actual production required an overhead cost of $280,000, $550,000 in materials used, and $220,000 in labor. All of the goods were completed. What amount was transferred to Finished Goods?