Draw the precedence diagram


Problem: The following tasks, which cannot be split, must be performed on an assembly line in the sequence and the times specified. The required cycle time is 75 seconds.

Task

Task time (Sec.)

Immediate predecessor

A

50

NONE

B

40

NONE

C

20

A

D

45

C

E

20

C

F

25

D

G

15

E

H

35

B,F,G,

 

250

 

-  Draw precedence diagram.

- Balance this line using the largest number of following tasks as the primary rule, and longest task time as the tie-breaker. What is the correct assignment of tasks to stations? (You will not necessarily use all of the stations listed, but you will definitely not need more than 5 stations.)