Draw the network flow diagram - identify the critical path


The following project data in the dependency table was provided by ABC Ltd IT manager; it relates to a new ICT project to be undertaken.

Activity

 

Duration (Days)

 

PrecedingActivities

 

Start Date

A

 

4

 

-

 

1/06/15

B

 

7

 

A

 

5/06/15

 

C

 

7

 

A

 

12/6/15

D

 

6

 

A

 

19/6/15

E

 

2

 

C

 

25/6/15

F

 

5

 

C

 

27/6/15

G

 

9

 

C

 

02/07/15

H

 

6

 

B, E

 

11/07/15

J

 

6

 

D, F

 

17/7/15

K

 

9

 

H, G, J

 

23/7/15

You are required to:

(i) draw the network flow diagram.

ii) Identify the Critical path and its duration.

(iii) Draw Gantt chart to illustrate the project.

Request for Solution File

Ask an Expert for Answer!!
Project Management: Draw the network flow diagram - identify the critical path
Reference No:- TGS01085960

Expected delivery within 24 Hours