A network consists of the activities in the following list. Times are given in weeks.

Activity

Preceding

Time

A

--

8

B

--

3

C

A

7

D

A, B

3

E

C

4

F

D

6

Requirements:

a. Draw the network diagram(AON Approach)

b. Calculate the ES, EF, LS, LF, and Slack for each activity.

c. Find the Critical Path

d. What is project completion time?