Draw the network diagram which activities form the critical


A network consists of the following list. Times are given in weeks.

Activity   Preceding   Duration

A -- 9

B A 2

C A 12

D A 5

E B 6

F B 8

G C, F 3

H D 2

I H 8

J G, I 6

K E, J 2

a. Draw the network diagram.

b. Which activities form the critical path?

c. How much slack exists at activities A and F?

d. What is the duration of the critical path?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Draw the network diagram which activities form the critical
Reference No:- TGS01672944

Expected delivery within 24 Hours