Draw the network calculate the earliest and latest time and


Question :Given the following information

Activity Duration (in days)

1-2 8
1-3 4
2-4 6
2-5 11
3-5 9
4-5 3
5-6 5
Required

a) Draw the network

b) Calculate the earliest and latest time

c) What is the critical path

d) What is the critical time