Q: Table below shows the activities, immediate predecessors and activity durations of a project. Draw the AON project network. How long would it take to complete this project? What is the length of the critical path?

Activity

Immediate Predecessor(s)

Duration (Days)

A - 2
B A 4
C A 4
D B 6
E D 9
F C 8
G

E, F

2
H G 2
I G 3
J

H, I

4
K J 4