Discuss the below in detail:
Q: Table below shows the activities, immediate predecessors and activity durations of a project. Draw the AON project network. How long would it take to complete this project? What is the length of the critical path?
| Activity |
Immediate Predecessor(s)
|
Duration (Days)
|
| A |
- |
2 |
| B |
A |
4 |
| C |
A |
4 |
| D |
B |
6 |
| E |
D |
9 |
| F |
C |
8 |
| G |
E, F
|
2 |
| H |
G |
2 |
| I |
G |
3 |
| J |
H, I
|
4 |
| K |
J |
4 |