Draw the aoa network and find the critical path time and


6_media_2be_2be85ed2-dc56-4ceb-b1fc-5737b1fcf787_phpJ010ol.png

Consider the following project (all times are in days).

1. Draw the AOA network and find the critical path, time and cost for an all-normal level of project activity.

2. Calculate the crash-cost per day (all activities may be partially crashed if possible)

3. Find the optimal way of getting an 18-day delivery time. What is the project cost?

4. Find the optimal way of getting an 16-day delivery time. What is the project cost?

5. Calculate the shortest delivery time for the project. What is the cost?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Draw the aoa network and find the critical path time and
Reference No:- TGS01681351

Expected delivery within 24 Hours