Question: The following tasks, which cannot be split, must be performed on an assembly line in the sequence and the times specified.

The required cycle time is 175 seconds.

Task

Task time (Sec.)

Immediate predecessor

A

50

NONE

B

40

NONE

C

20

A

D

45

C

E

20

C

F

25

D

G

15

E

H

35

B,F,G,

 

250

 

-  Draw precedence diagram.