Draw by hand the bar chart gantt chart with logic links and


Question: Draw by hand the bar chart (Gantt chart) with logic links and draw by hand the activity-on-node (AON) network diagram showing the schedule for the following project, including the full logic and a legend. Complete the forward pass and backward pass calculations to determine the early start (ES), late start (LS), early finish (EF), late finish (LF), total float (TF), and free float (FF) for each activity. Write all numerical results into the AON network Highlight the critical path in the network and the bar chart and determine the total project duration. Provide a table that includes the activity list below and the numerical results in six additional columns. Mark critical activities in boldface in the table. Do not use software for this assignment.